8-MG & 2-MG Steel Reservoirs Paint and Repairs
Project Information
Project Name
8-MG & 2-MG Steel Reservoirs Paint and Repairs
Project Type
Reservoir
Project Manager
Marcelo Anglade
Project Description
The 8-MG and 2-MG steel reservoirs included in this project will inspected and recoated as determined during the predesign phase. In addition to the repairs recommended in the inspections reports, the reservoirs will have minor feature modifications such as new access ladders and large access ports.
Prequalification Submittals Due
3/24/2022
Estimated RFP Release Date
March 10, 2022
Engineering Contract Date
4/13/2022
Contact/Planholders List
This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.
Public Notices
There are no public notices at this time.
Contract Documents and Project Information
There are no documents attached to this project.