Project Details

Engineering project details, documents, and contact information can be found below.

JVWTP Replace Air Scour Piping

Project Information

Project Name
JVWTP Replace Air Scour Piping
Project Type
Treatment
Project Manager
David McLean
Project Description
This project replaces corroded 16" air scour piping in the sixteen filters at the Jordan Valley Water Treatment Plant.
Consultant
Brown and Caldwell
Estimated Bid Documents Available
4/2/2019
Estimated Construction Cost
$1,500,000 - $2,000,000

Contact/Planholders List

This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.

Download List

Public Notices

6/6/2019 - Notice of Award

On June 5, 2019, the JVWCD Board of Trustees awarded a construction contract to VanCon, Inc. for Jordan Valley Water Treatment Plant Air Scour Piping Replacement in the amount of $1,458,000.    Additional information will be made available as allowed by law.

Contract Documents and Project Information

There are no documents attached to this project.