Project Details

Engineering project details, documents, and contact information can be found below.

JVWTP Air Scour Blower Purchase

Project Information

Project Name
JVWTP Air Scour Blower Purchase
Project Type
Treatment
Project Manager
David McLean
Project Description
Purchase one replacement air scour blower for the Jordan Valley Water Treatment Plant.  The existing blower is 30 years old and has failed. The new blower will have a flow of 5200 cfm at 6.5 psi.  Installation will be by JVWCD staff
Estimated RFP Release Date
12/6/2018
Engineering Contract Date
9/1/2018
Consultant
Brown and Caldwell
Estimated Bid Documents Available
12/6/2018
Bids Due
12/20/2018 1:00 PM
Estimated Construction Cost
$250000

Contact/Planholders List

This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.

Download List

Public Notices

12/5/2018 - Announcement

Bid documents have been posted to the Jordan Valley Water Conservancy District web site for purchase of one replacement
air scour blower for the Jordan Valley Water Treatment Plant.  Bids are due December 20, 2018.  

Contract Documents and Project Information

Date Type Description Download
12/6/2018 Bid Documents Bid Documents Download