Project Details

Engineering project details, documents, and contact information can be found below.

JVWTP Reclaim Water Improvements

Project Information

Project Name
JVWTP Reclaim Water Improvements
Project Type
Treatment
Project Manager
David McLean
Project Description
Recommended improvements include concrete "scalping" control box, 1500 LF of 14" pipeline design,  2000 LF of 24" HDPE , replacement of two vertical turbine pumps, and pump house modifications to accommodate the new pumps.  The project will also provide concrete lining for the existing washwater basins.
Estimated RFP Release Date
12/10/2018
Engineering Contract Date
3/13/2019
Consultant
Carollo Engineers
Estimated Bid Documents Available
7/28/2020
Construction Contract Date
10/14/2020
Bids Due
8/20/2020 3:00 PM
General Contractor
Nelson Brothers Consstruction Company
Estimated Construction Cost
$3,600,000- $4,200,000

Contact/Planholders List

This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.

Download List

Public Notices

10/14/2020 - Announcement

The JVWCD Board of Trustees approved a construction contract award to Nelson Brothers Construction Company in the amount of $2,864,643 for construction of JVWTP Reclaim Water and Solids Handling Improvements.  Additional information is available as allowed by law.

9/11/2020 - Bid Results

Bids have been received for the JVWTP Reclaim Water and Solids Handling Improvements Project.  The apparent low bidder is Nelson Brothers Construction Company.  Additional information is available as allowed by law.

Contract Documents and Project Information

Date Type Description Download
9/11/2020 Bid Results Bid Results Download
9/8/2020 Addendum Addendum #4 Download