This project includes the supply and installation of one new 6,000 gallon sodium chlorite tank to operate in parallel with the two existing tanks.  Tanks are to meet the original specifications and submittals for the two original tanks purchased in year 2010.  Installation is on an existing pad via an existing roll-up door each sized for this purpose.
Consultant
JVWCD Staff
Estimated Bid Documents Available
9/29/2019
Estimated Construction Cost
$60,000 - $70,000

Contact/Planholders List

This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.

Download List

Public Notices

10/4/2019 - Bid Documents Addendum

Addendum # 1 for the Sodium Chlorite Tank Supply and Installation project has been posted.  This addendum offers clarifications regarding questions posed at the non-mandatory pre-bid meeting held at the site on October 3, 2019.  If a bidder was not able to attend the pre-bid, yet would like a tour of the facility, please contact Steve Blake at 801-446-2003.

10/4/2019 - Bid Documents Addendum

Addendum # 1 for the Sodium Chlorite Tank Supply and Installation project has been posted.  This addendum offers clarifications regarding questions posed at the non-mandatory pre-bid meeting held at the site on October 3, 2019.  If a perspective bidder was not able to attend the pre-bid, yet would like a tour of the facility, please contact Steve Blake at 801-446-2003.  The bid date and time remain unchanged as October 17, 2019 at 1:00 pm.  

9/27/2019 - Announcement

We have received several reports of the website being not available.  If you hit on the name not the "new" it works.  We are trying to find out why.

Here is a path that works:

https://jvwcd.org/project/233/sodium-chlorite-tank-supply-and-installation

https://jvwcd.org/project/233/sodium-chlorite-tank-supply-and-installation

9/26/2019 - Bid Documents Available

Bid Documents are now available for the JVWTP Sodium Chlorite Tank Project. This project includes the supply and installation of one new 6,000 gallon sodium chlorite tank to operate in parallel with the two existing tanks.  Tanks are to meet the original specifications and submittals for the two original tanks purchased in year 2010.  Installation is on an existing pad via an existing roll-up door each sized for this purpose.

Contract Documents and Project Information

Date Type Description Download
10/4/2019 Addendum Addendum 1 Download
9/26/2019 Bid Documents Bid Documents Download