3300 South Pipeline Project - Phase 2

Project Information

Project Name
3300 South Pipeline Project - Phase 2
Project Type
Pipeline
Project Manager
Kevin Rubow
Project Description
Replacement of existing 8" cast iron waterline installed in 1956 located along 3300 South from 500 West to State Street. The existing waterline will be replaced with 12" pipe, approximately 5,000 feet of pipeline will be installed with this project. The pipeline installation will include open-cut, directional drilling, and slip-line methods.
Consultant
Bowen, Collins & Associates
General Contractor
Beck Construction; Vancon Inc.
Estimated Construction Cost
$6.2 million

Contact/Planholders List

This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.

Download List

Public Notices

There are no public notices at this time.

Contract Documents and Project Information

There are no documents attached to this project.