700 E and 1000 E Well Equiping

Engineering project details, documents, and contact information can be found below.

700 E and 1000 E Well Equiping

Project Information

Project Name
700 E and 1000 E Well Equiping
Project Type
Well House
Project Manager
Kevin Rubow
Project Description
Construction of two deep well pump stations at two separate sites located at 7618 South 700 East, Sandy City and 7750 South 1000 East, Midvale City.
Consultant
Hansen, Allen & Luce
General Contractor
Whitaker Construction
Estimated Construction Cost
$8.2 million

Contact/Planholders List

This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.

Download List

Public Notices

1/8/2025 - Announcement

On January 8, 2025, an Award of Construction Contract was approved by the JVWCD Board of Trustees with Whitaker Construction for the 700 E and 1000 E Well House Construction project. Additional information is available as allowed by law.

12/19/2024 - Bid Results

Bids for the 700 E & 1000 E Well House Construction project were opened at 3:00 pm on Thursday, December 19, 2024. The Bid Results are posted on the Project Webpage. JVWCD expresses its appreciation for the time and effort from all those who were involved in the bidding process.

Contract Documents and Project Information

Date Type Description Download
12/19/2024 Bid Results Bid results Download