Project Information

Project Name
Digital Twin Pilot at SERWTP
Project Type
Engineering Studies
Project Manager
Conor Tyson
Project Description
The SERWTP was built to utilize stream flows that JVWCD has water rights in the eastern hills. However, as this water is only available for a few months a year, it is desirable to maximize the runoff water the plant can treat. This project seeks to develop a Digital Twin Pilot using data from the treatment plant to determine how to maximize runoff water utilization while minimizing costs. It is anticipated that the resulting pilot would be incorporated into continuing plant operation.
Estimated RFP Release Date
May 2025
Proposals Due
6/26/2025 3:00 PM
General Contractor
N/A
Estimated Construction Cost
$400,000-$700,000

Contact/Planholders List

This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.

Download List

Public Notices

5/27/2025 - Request for Proposal Issued

A Request for Proposals for Developing an Online Digital Twin for the SERWTP has been issued. Obtain RFP documents through www.jvwcd.org under the Engineering Projects link. Written Qualifications Proposals are due by 3:00 pm on Thursday, June 26, 2025. Any questions should be directed to the project manager, Conor Tyson.

Contract Documents and Project Information

Date Type Description Download
5/27/2025 Request for Proposal Request for Proposals Download
2/26/2025 Requests for Information Request for Information Download
2/26/2025 Attachment Non-Disclosure Agreement Download