Jordan Valley Water Treatment Plant Backwash Outlet Valve Replacements
Project Information
Project Name
Jordan Valley Water Treatment Plant Backwash Outlet Valve Replacements
Project Type
Valve & Meter Vaults
Project Manager
John Kahle
Project Description
This work includes replacing two 36” butterfly valves with new electronically actuated valves located on the outlet structure of the backwash reclamation ponds at the Jordan Valley Water Treatment Plant (JVWTP). The work also includes running two conduits to provide power to the actuators and new outlet receptacles.
Estimated Bid Documents Available
February 2025
Construction Contract Date
4/9/2025
Bids Due
3/20/2025 3:00 PM
Contact/Planholders List
This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.
Public Notices
3/25/2025 - Bid Results
Bids for the JVWTP Backwash Outlet Valve Replacement project were opened at 3:00pm on Tuesday, March 25, 2025. The Bid Results are posted on the Project Webpage. JVWCD expresses its appreciation for the time and effort from all those who were involved in the bidding process.