Project Details

Engineering project details, documents, and contact information can be found below.

2023 Distribution Pipeline Replacements - Old Farm and 5650 South Areas

Project Information

Project Name
2023 Distribution Pipeline Replacements - Old Farm and 5650 South Areas
Project Type
Pipeline
Project Manager
Conor Tyson
Project Description
The replacement of existing cast iron retail distribution pipeline installed in the 1950s and 1960s. This project area will primarily be in Murray Utah. Project includes utility surveying and actual pipeline replacements.
Consultant
Project Engineering Consultants
Estimated Bid Documents Available
January 2023
Bids Due
1/24/2023 11:00 AM
Estimated Construction Cost
$1,800,000 - $2,500,000

Contact/Planholders List

This list includes engineers, contractors, subcontractors, suppliers, and others associated with this project. You MUST sign up to receive addenda and revisions, project notifications and other project information.

Download List

Public Notices

1/24/2023 - Bid Results

Bid results for the 2023 Distribution Pipeline Replacement - Old Farm and 5650 South Areas Project were received on January 24, 2023 at 11:00 am. The results of the bids are posted on the district website. The district expresses its appreciation for the time and effort it takes to provide a bid for a project. Additional information is available as allowed by law.

Contract Documents and Project Information

Date Type Description Download
1/24/2023 Bid Results Bid Results Download
1/5/2023 Bid Documents Bid Documents Download
1/5/2023 Drawings Bid Drawings Download